Aykley Head, Durham

Helical Displacement Inclusion

CLIENT

Durham County Council

DEVELOPER

Durham County Council

SCOPE OF WORKS 

Helical Displacement Inclusion

PROJECT BRIEF

Roger Bullivant was approached by the technical team at Durham County Council to assist with a foundation solution for a new office building on Plot C at Aykley Heads, Durham.

The development formed part of a wider scheme to develop the Aykley Heads area as part of the council’s plan to relocate its current HQ. The area is already home to a number of businesses and the re-development aims to attract thousands of high-quality jobs, worth up to £400 million to the county’s economy.

KEY ISSUES

Roger Bullivant was requested to provide guidance and a solution for the use of a rigid inclusion ground improvement technique to provide an adequate bearing for 20kPa and 200kPa bearing pressures for the internal slab and steel portal frame structure.

Ground conditions generally comprised of loose to medium dense sands overlying medium dense to dense sands.

RB’s Helical Displacement Inclusion (HDI) technique was proposed adopting a 300mm/600mm column to 8m depths beneath strip and pad locations and a 5m depth for the slab areas.

The basic principle behind the HDI process is to offer settlement reduction through the installation of concrete inclusions below a load transfer platform to distribute the load imposed by the slab. The inclusions act as a reinforcing element within the soil profile and rely on the interaction between the load transfer mat, soil, and inclusion to support the structure.

A finite element design was undertaken to evaluate the predicted settlements for the applied loads. The proposed 5m and 8m HDI’s with a 400mm deep load transfer platform formed the final design.

SOLUTION

RB installed 227 Nr. 300mm/600mm HDI’s to depths of 8m underneath all pad and strip foundation locations and 175 Nr. 300mm/600mm HDI’s to depth of 5m for the area underneath the slab.

HDI’s were validated by carrying out a series of plate load tests and a zone test to ensure that the recorded settlements were in accordance with the design calculations.

Despite encountering one area on site which contained some obstructed ground that required some additional pre-boring work, RB completed the ground improvement works on budget and within the scheduled programme time.

The benefits of the HDI technique allow for a thinner ground bearing slab, vibration-free installation, minimal spoil removal, easier trimming of the columns.

Durham County Council, Construction Manager said:
“I found Roger Bullivant as a contractor to be very professional throughout, from pre-construction to the works being completed on site. I would have no hesitation in using them again on any future projects.”

GET IN TOUCH

RB Breakfast Club

Apply for an invite to our breakfast club events

  • This field is for validation purposes and should be left unchanged.